PROJECT DESCRIPTION

Project Limits

I-95 from 12th Avenue South to 10th Avenue North

Purpose

Improve roadway capacity, safety and efficiency.

Scope of Work

FDOT is widening I-95 from six lanes to ten lanes along this section, a length of approximately 1.8 miles.  The work includes widening the existing Lake Worth Viaduct bridge, replacing the existing bridge over 6th Avenue South, and reconstructing the mainline ramps.  The project will also include drainage improvements, sound barrier walls, retaining walls, signing and pavement marking, lighting, landscaping, irrigation, and communication elements.

Construction Timeline

Begin Construction: July 2004
End Construction: February 2008

Maintenance of Traffic

Lane closures on I-95 will only occur at night when traffic volumes are lighter. Three thru lanes will be maintained at all times from 5:30 am to 8:00 pm. There will also be ramp closures as follows:

Southbound I-95 to 6th Avenue South off-ramp – 190 days
6th Avenue South to Southbound I-95 on-ramp – 148 days
Northbound I-95 to 6th Avenue South off-ramp – 119 days
6th Avenue South to Northbound I-95 on-ramp – 167 days
10th Avenue North to Southbound I-95 on-ramp – 24 days

Advance warning of ramp work will be provided.

Full closure of 6th Avenue will be allowed in the immediate proximity of the bridge (South “A” Street to Barber Avenue) between the hours of 9:00 pm and 6:00 am for bridge demolition, beam placements, and deck pours for the new bridge.  Detour plans shall be implemented to accommodate both directions of traffic during the times of full closure.

Construction Phasing

Phase I

This phase will begin with the construction of the Lake Worth High School off-site parking lots.  No work will begin on I-95 until the LWHS parking lots are completed.  Noise walls along the east side of I-95 between 12th Avenue North and 6th Avenue South and between Lake Worth Road and 10th Avenue will be constructed.  I-95 Traffic will be shifted towards the outside of the existing roadway to accommodate the temporary road construction in the existing median.  Lake Worth Road will be milled and resurfaced and widened to the outside and reconstruction of 6th Avenue eastbound roadway will be done in this phase.

Phase II-

Southbound traffic will be diverted to the newly constructed median area as the road and bridge improvements on the southbound side of I-95 are constructed.  Ramps on the southbound side of I-95 will be reconstructed.  Closures for those ramps will be during this phase.  Construction of 6th Avenue westbound roadway and Lake Worth Road median construction will be done in this phase.

Phase III

Northbound traffic will be diverted to the previously constructed median, and the southbound traffic will be on the newly constructed southbound roadway area as the road and bridge improvements on the northbound side of I-95 are constructed.  Ramps on the northbound side of I-95 will be reconstructed.  Closures for those ramps will be during this phase.  Construction of 6th Avenue median will be done in this phase.

Phase IV

Complete the construction of the road in the median as northbound and southbound traffic use the newly constructed roadway.

Factoids

Over 3 million pounds of steel and 17 million pounds of concrete will be used to widen the Lake Worth Viaduct bridge.
Over 175 miles of permanent and temporary striping will be used—enough to reach from West Palm Beach to Orlando!
There are 138 lights in only a 1.8 mile stretch of roadway.