CONTRACT DETAILS

FIN #231918-2-52-01, 231919-2-52-01

Federal Aid #0951 576 I, 0951 582 I

From 10th Avenue N.
To south of SR 80

Description of Work:
The work includes the widening and reconstruction of I-95 from 10th Avenue North to South of SR 80. The work includes the widening of the 17th Avenue bridge, the widening of the Forest Hill Boulevard Overpass and the reconstruction of the bridge over the C51 canal. Other improvements consists of drainage enhancements, sound barrier walls, retaining walls, signing and pavement marking, lighting, landscaping, irrigation and communications elements.

Contractor
Hubbard Construction

Joe Kanaday
jkanaday@hubbard.com
(561) 272-8882

Letting

07/30/03

Contract

T4016

Resident Engineer

Eduardo Perez de Morales, P.E.
eperez@corradino.com
(561) 805-7550 x1121

Award

09/12/03

Construction Time

1543 CD

FDOT Project Manager

Courtney Drummond, P.E.
courtney.drummond@dot.state.fl.us
(954) 777-4379

Executed

10/01/03

Contract Amount

$44,983,454.84

Project Administrator



Area Engineer

Scott Cavendish
scavendish@i95wpb.com
(561) 697-2522

Greg Lady, P. E.
glady@i95wpb.com
(561) 805-7550

NTP

10/30/03

Earned to Date

$45,449,593.78

Design Project Engineer

James Hughes, P.E.

james.hughes@dot.state.fl.us

(954) 777-4445

 

Jean N. Hanna, M.S.C.E., E.I.
jean.hanna@dot.state.fl.us
(954) 777-4440

Begin Construct.

04/14/04

Estimated Completion

06/02/08

Design Firms
HDR Engineering Inc.

Reynolds, Smith & Hills, Inc.

 

Larry Low, P.E

llow@hdrinc.com

(813) 282-2349

 

 

Phil Schwab, P.E.

phil.schwab@rsandh.com

(954) 474-3005

Contract Completion

01/12/08

Number of Days Used

1596

Special Considerations:

No Excuse Bonus:
The No Excuse Bonus concept is to provide the contractor with substantial incentive to complete a project within a specified time frame regardless of any problems or unforeseen conditions that may arise.

Bonus #1: $2,500,000 to complete the contract in 1150 days.
Bonus #2: $25,000 to complete 10th Ave North SB Off-Ramp (Ramp 2-D1) in 28 consecutive days from initial closure.
Bonus #3: $25,000 to complete 10th Ave North NB On-Ramp (Ramp 2-C1) in 35 consecutive days from initial closure.
Bonus #4: $25,000 to complete Forest Hill Blvd NB Off-Ramp (Ramp 3-B1) in 9 consecutive days from initial closure.

Incentive/Disincentive:
The Incentive/Disincentive concept is used to expedite the completion of certain aspects of the project.  The number of I/D days will not be changed for any reason, including, but not limited to, work added, work deleted, bad weather, unforeseen conditions, etc.

Ramp 2-D1 (10th Avenue N SB Off-Ramp): I/D daily amount of $7,500. Max I/D: $75,000; Max closure time 28 days.
Ramp 2-C1 (10th Avenue N NB On-Ramp): I/D daily amount of $7,500. Max I/D: $75,000; Max closure time 35 days.
Ramp 3-B1 (Forest Hill Blvd NB Off-Ramp): I/D daily amount of $10,000. Max I/D: $50,000; Max closure time 9 days.

Other Special Provisions:
Article 7-11.3.1: Hauling and staging: Prohibits the contractor from parking, staging and/or hauling material and equipment using local surface streets.

Article 8-3.3: Prosecution of Work- Flexible Start Time: Allows the contractor to procure material. It requires the contractor to obtain an approved schedule. Trainee requirements are identified and a trainee schedule is submitted and approved by the Department. Submittal of all critical shop drawings and attend a mandatory constructability workshop.

Article 8-3.7: Disputes Review Board: The Board will provide special expertise to assist in and facilitate the timely and equitable resolution of disputes, claims, and controversies between the Department and the Contractor in an effort to avoid construction delay and future claims.

Article 8.4-10: Protection of Adjacent Properties: Any equipment used by the Contractor for this project shall not exceed vibration levels of 0.20 inch per second at any point within 400 feet of the right of way. The Contractor shall employ a qualified Specialty Engineer to monitor and record vibration levels produced by vibratory construction equipment used on this project.  The Contractor shall perform a Pre-Construction survey with the use of video and still photography on each property, located within 400 feet from the Right of Way, identifying the existing structural conditions, of the property or any other improvement of such property which may be affected by vibration.

Article 8-4.11: Noise Restrictions: Equivalent sound levels shall not exceed 50dba Monday - Friday from 8 p.m. to 8 a.m., all day Sunday and during legal holidays.

Article 102-3.3: Sequence of Operations: Construction of the project north of Forest Hill Boulevard is not to begin until Phase III is complete.  This is to prevent any possible conflicts with the construction of the SR 80 interchange.

Article 104-7.3: Routine Maintenance: Sweep the I-95 roadway and bridge surfaces every 14 days, and the side streets every 7 days.  Provide daily clean up of litter, debris and dirt from local streets and properties. Failure to clean up in 12 hours, FDOT has right to clean up and back-charge the contractor.