Project
Limits |
|
·
I-95 from south of Southern Blvd (SR 80) to north of Southern
Blvd (SR 80)
· SR 80
from Gem Lake Drive to Parker Avenue |
 |
Purpose |
|
Improve capacity, roadway safety
and efficiency. |
 |
Scope of Work |
|
The improvements on this project
consist of major interchange improvements at the intersection of SR 80
(Southern Boulevard) and I-95. The work includes new construction of the
bridges over I-95 and the RR, resurfacing, structural work, signing, signalization,
landscaping and lighting. |
 |
Construction Timeline |
|
Begin Construction:March 2004
End Construction: October 2006 |
 |
Maintenance of Traffic |
|
Lane
closures on I-95 will only occur at night when traffic volumes are lighter.
Three thru lanes will be maintained at all times from 5:30 am to 8:00
pm. There will also be ramp closures as follows:
Southbound I-95 to SR 80 off-ramp and SR 80
to Northbound I-95 on-ramp concurrently– 30 days
Northbound I-95 SR 80 off-ramp and SR 80 to Southbound I-95 on-ramp concurrently–
30 days
Advance warning of ramp work will be provided.
Lane closures on SR 80 will only occur at night when traffic volumes are
lighter. Two thru lanes will be maintained at all times from 5:30 am to
7:30 pm west of I-95 and from 6:00 am to 6:00 pm east of I-95. In addition,
no lanes should be closed from Friday 5:00 am thru Sunday 10:30 pm.
On SR 80 pedestrian, bicycle, and wheelchair access will be maintained
on at least one side of the project at all times. |
 |
Construction Phasing |
|
Phase I |
|
SR 80. Traffic will be shifted
to the outside. Remove all traffic separators and place temporary asphalt
in the median.
I-95. Traffic will be reduced to three lanes in each direction and maintained
on the existing roadway while work is being done on the shoulders and
in the median. Three of the four ramps will be reduced to one lane as
construction begins. |
|
Phase II |
|
SR 80. Shift westbound traffic to the newly constructed median pavement.
Construct new westbound lanes. Demolish and reconstruct westbound bridges over Stub Canal and I-95.
I-95. Traffic will be switched between the northbound and southbound lanes as needed for bridge work
being done above. Three lanes of traffic will be open in each direction. Ramp work will continue on
all four ramps. Temporary concurrent ramp closures on the southbound I-95 to SR 80 off-ramp and SR 80
to northbound I-95 on-ramp will be made as the connections to SR-80 are being constructed. |
|
Phase III |
|
SR 80. Shift traffic to the newly constructed westbound pavement. Construct new eastbound lanes. Demolish and reconstruct eastbound bridges over Stub Canal and
I-95.
I-95. Traffic will be switched
between the northbound and southbound lanes as needed for bridge work
being done above. Three lanes of
traffic will be open in each direction. Ramp work will continue on all four ramps. Temporary concurrent ramp closures on the northbound I-95 SR 80
off-ramp and SR 80 to southbound I-95 on-ramp will be made as the connections
to SR-80 are being constructed. |
|
Phase IV |
|
SR 80. Traffic will be shifted to the outside of the newly constructed
lanes while the median is constructed.
I-95. Traffic will be restored to four lanes in each direction as the road is being milled and resurfaced.
|
|
Phase V |
|
SR 80. The final lifts of asphalt will be placed during this stage.
I-95. Traffic will be shifted
to the outside as the median is reconstructed. |
|
Phase VI |
|
I-95.
Traffic will be maintained in its final configuration as shoulder
work is completed. Ramps will be completed in this phase. |
|
Phase VII |
|
I-95.
The final lifts of asphalt will be placed during this stage. |
 |
Factoids |
|
Over 30.5 miles of temporary barrier wall will be used during construction.
Over 216 miles of temporary striping will be placed during the construction! |