PROJECT DESCRIPTION

Project Limits

I-95 from north of Blue Heron Boulevard to south of PGA Boulevard

Purpose

Improve capacity, roadway safety and efficiency.

Scope of Work

FDOT is widening I-95 from six lanes to ten lanes along this section, a length of approximately 2.6 miles. The work includes replacing the existing bridges over Northlake Boulevard, Holly Drive and Burns Road. Auxiliary lanes will also be added along portions of the mainline between interchanges. The construction will include modifications to the mainline and mainline ramps as well as modifications to the side streets and side street ramp terminals at Northlake Boulevard and PGA Boulevard. The project will also include drainage improvements, sound barrier walls, retaining walls, signing and pavement marking, signalization, lighting, landscaping, and irrigation and communications elements.

Construction Timeline

Begin Construction: August 2002
End Construction: September 2006

Maintenance of Traffic

Lane Closure on I-95 will only occur at night when traffic volumes are lighter. Three thru lanes will be maintained at all other times.

One ramp at a time at the Northlake interchange will be closed for 30 days each as the ramps are reconstructed. Advance warning of the ramp work will be provided.

A minimum of two thru-lanes and one left-turn lane shall remain open on Northlake Boulevard in each direction between the hours of 6:00 AM and 9:00 PM. Full closures of the eastbound lanes and westbound lanes (never both at the same time) will be allowed between the hours of 9:00 PM and 6:00 AM for demolition of the existing bridges and beam placements/deck pours for the new bridge. During those closures, traffic for the closed direction will be shifted to cross I-95 under the span for the opposing direction. Pedestrian and bicycle travel ways will be provided for.

Full closure of Holly Drive will be allowed in the immediate proximity of the bridge (Plant Drive to Dasheen Avenue) between the hours of 9:00 PM and 6:00 AM for beam placements/deck pours for the new bridge. Detour plans shall be implemented to accommodate both directions of traffic during the times of full closure. Pedestrian and bicycle traffic will be provided for.

Construction Phasing

Phase I

Noise walls along both sides of I-95 will be constructed in this phase. Traffic will be shifted towards the outside of the existing roadway to accommodate the temporary road and bridge construction in the existing median.

Phase II

Southbound traffic will be diverted to the newly constructed median area as the road and bridge improvements on the southbound side of I-95 are constructed.

Phase III

Northbound traffic will be diverted to the previously constructed median and the southbound traffic will be on the newly constructed southbound roadway area as the road and bridge improvements on the northbound side of I-95 are constructed.

Phase IV

Complete the construction of the road and bridge improvements in the median as northbound and southbound traffic use the newly constructed roadways.

Phase V

Traffic will be shifted into its final configuration as the roadway is resurfaced.

Factoids

Over 2 million pounds of steel and 34 million pounds of concrete will be used to construct the noise walls!
Over 85,000 linear feet of new striping will be placed along the project. That is over 280 football fields!